Electric Vehicle Supply Equipment (EVSE) Plan

Need Help? Something Missing?

Email the Technical Response Service or call 800-254-6735.

The Utah Department of Transportation (UDOT) must lead state agencies in the creation of a statewide EVSE plan to provide electric vehicle charging facilities along certain state highways at distances no greater than every 50 miles. EVSE locations must be determined by June 30, 2021, and installed by December 31, 2025. UDOT must submit a report outlining the plan by November 30, 2020.

(Reference Utah House Bill 259, 2020, and Utah Code 72-1-215)